Implementing Sector: | State |
Category: | Regulatory Policy |
State: | Massachusetts |
Incentive Type: | Interconnection |
Web Site: | https://sites.google.com/site/massdgic/home/interconnection |
Eligible Renewable/Other Technologies: | Geothermal Electric, Solar Thermal Electric, Solar Photovoltaics, Wind (All), Biomass, Hydroelectric, Municipal Solid Waste, Combined Heat & Power, Fuel Cells using Non-Renewable Fuels, Landfill Gas, Wind (Small), Fuel Cells using Renewable Fuels, Other Distributed Generation Technologies, Microturbines |
Name: | S.B. 2395 (Session Law Chapter 209) |
Date Enacted: | 08/03/2012 |
Name: | Order No. 11-75-E |
Date Enacted: | 3/13/2013 |
Name: | Order No. 11-75-E Appendix A |
Date Enacted: | 3/13/2013 |
Name: | Order 11-75-F |
Date Enacted: | 07/31/2014 |
Massachusetts' interconnection standards apply to all forms of distributed generation (DG), including renewables, and to all customers of the state's three investor-owned utilities (Unitil, Eversource, and National Grid).
Massachusetts requires investor-owned utilities to have standard interconnection tariffs. There are three basic paths for interconnection in the state:
The issue of interconnection to network systems is particularly important in Massachusetts because network systems are commonly used in dense urban areas, such as Boston. Order 11-75-E implemented a more transparent Supplemental Review screen process for projects that fail the initial Simplified and Expedited screens. If a project fails the Simplified and Expedited screens, it must pass three supplemental review screens, otherwise it must go through the full standard review process. Massachusetts uses a 100% of minimum load penetration screen in the supplemental review process. If the generating capacity is less than 100% of minimum load, it may not require a detailed study. In addition to these different paths, for all systems 500 kW or greater, facility owners must request and receive a pre-application report from the utility. The pre-application report is optional for facilities less than 500 kW; no fee is charged for this report.
For the simplified and expedited interconnection paths, technical requirements are based on the IEEE 1547 and UL 1741 standards. A manual external disconnect switch may be required at the discretion of the utility (project-specific, not required in the tariffs). Utilities must collect and track information on the interconnection process. This information will be used in revising and updating the standards.
History
In August 2011, the Department of Energy Resources (DOER) submitted the Massachusetts Distributed Generation Interconnection Report to the Department of Public Utilities (DPU) outlining its recommendations for improved interconnection policies and processes based on its research, which included an extensive stakeholder survey, conducted in April 2011. In September 2012, the Massachusetts Distributed Generation Interconnection Working Group submitted its final report recommending changes to the state's interconnection standards. DPU incorporated changes from comments submitted in Docket 11-75, and adopted the report those changes in March 2013.
Input your address to see if it is solar friendly and how much you can save with solar.
Great. Your address is perfect for solar. Solar incentive is still available. Select monthly utility cost and calculate the size of solar system you will need now.
kw System size | years Payback period | Lifetime savings |
No money down, 100% finance is available.
Explore New Solar Potentials with NEM 3.0 on HahaSmart
April 26, 2023NEM 3.0 Goes Live in California: What It Means for EPCs and Homeowners?
April 13, 2023Increase Your Solar Sales with Our New Feature: Solar Access with Google Sunroof
March 28, 2023Homeowner Profiles Connect with Solar Pros
March 2, 2023